Barn conversion timeline

Build-cost bands are the site's own indicative model, inflated to a Q2 2026 footing via the ONS Construction Output Price Index (April 2026). Class Q rules current to the 21 May 2024 GPDO amendment.

A typical UK barn conversion runs 18 to 24 months end to end. Class Q route can compress to 14-18 months on a sound barn; full planning with listed-building consent regularly extends to 26-30 months.

The five phases

  1. Feasibility and design (8-16 weeks): survey, structural appraisal, RIBA Stage 0-2.
  2. Planning (8-24 weeks): Class Q 56 days + responses, or full planning 13 weeks + conditions discharge.
  3. Tender and pre-construction (8-12 weeks): RIBA Stage 4, contractor tender, building control.
  4. Construction (28-50 weeks): strip-out, shell, M&E first fix, internal fit, snagging.
  5. Completion and VAT reclaim (4-12 weeks): completion certificate, six-month VAT431C window.

Where programmes slip


Reviewed for build by O. Wakefield-Smith, Digital Signet research, Q2 2026. A chartered surveyor (RICS MRICS) sign-off is being procured for the live site. Statutory and tax figures bracket their published ONS, gov.uk or HMRC source on the page where they appear; the £/m² build-cost bands are the site's own indicative model, not a published dataset.