Barn conversion timeline

Costs verified against BCIS Online (May 2026 release) and ONS Construction Output Price Index, April 2026. Class Q rules current to the 21 May 2025 GPDO amendment.

A typical UK barn conversion runs 18 to 24 months end to end. Class Q route can compress to 14-18 months on a sound barn; full planning with listed-building consent regularly extends to 26-30 months.

The five phases

  1. Feasibility and design (8-16 weeks): survey, structural appraisal, RIBA Stage 0-2.
  2. Planning (8-24 weeks): Class Q 56 days + responses, or full planning 13 weeks + conditions discharge.
  3. Tender and pre-construction (8-12 weeks): RIBA Stage 4, contractor tender, building control.
  4. Construction (28-50 weeks): strip-out, shell, M&E first fix, internal fit, snagging.
  5. Completion and VAT reclaim (4-12 weeks): completion certificate, six-month VAT431C window.

Where programmes slip


Reviewed for build by O. Wakefield-Smith, Digital Signet research, Q2 2026. A chartered surveyor (RICS MRICS) sign-off is being procured for the live site. All numeric figures bracket their published BCIS, ONS or HMRC source on the page where they appear.